Olga, the last of the project’s tunnel boring machines, has completed excavation work on the Brenner Base Tunnel, hitting a major milestone.

The task for the machine was to excavate a tunnel of about 7.6 kilometers on the construction section H53 Pfons-Brenner between 18 September 2024 and 24 November 2026. Its breakthrough completes mechanized excavation for the Brenner Base Tunnel after its work on the eastern main tunnel heading to Innsbruck.

Wolfgang Holzer, Construction Director for the Innsbruck-Brenner section, emphasized the team effort behind this success. "Specialists, experienced construction teams and the latest technologies have been working hand in hand for years.

The milestone is the culmination of a complex excavation program, utilizing nine tunnel boring machines, each engineered and configured to suit the specific technical and geological demands of its allocated section.

Nine specialised tunnel boring machines deployed across the project

A total of nine TBMs have been used during construction of the Brenner Base Tunnel, eight of which were manufactured by German company Herrenknecht.

Rather than relying on identical equipment throughout the project, each machine was specifically adapted to the conditions of its excavation section. Differences in rock characteristics and the required excavation power determined the configuration of the cutting head and the technical equipment installed on each TBM.

Olga was among the largest machines deployed, measuring approximately 183 metres in length and weighing around 2,600 tonnes.

Its technical specifications included a cutting head with a diameter of 10.37 metres, an installed power capacity of 4,550 kilowatts and a torque of 26,400 kilonewton metres.

How Olga finished its excavation mission

The machine worked by combining the excavation and the tunnel lining.

Its rotating cutting head bored through the surrounding rock, while conveyor belts removed the excavated material from the work area.

At the same time, Olga was fitting prefabricated concrete segments together to form the tunnel’s structural lining, which meant the excavation and lining could be done as part of the same mechanized construction process.

But to keep progressing it needed constant tweaking during the work.

Michael Knapp, project manager for the H53 construction section, said excavation operations had to be adjusted regularly to changing geological conditions. Another important aspect was to coordinate the TBM performance with the different activities related to the excavation process, so as to keep an efficient construction sequence.

Mechanized excavation done in the Brenner Base Tunnel

The last tunnel boring machine still working, Olga, broke through on 24 November 2026. The mechanized excavation phase of the Brenner Base Tunnel is now over.

The feat underlines the sheer scale of the engineering feat, which required nine specialist machines, a wealth of technical know-how and long-term coordination between construction crews.

With the final TBM completing its assigned work, the project has reached a major milestone in the construction of one of Europe’s major cross-border rail infrastructure projects.