Rijeka Port Awards €11.5 Million Contract for Shore Power Infrastructure
Croatian company Končar will design and install cold ironing systems at the AGCT and Rijeka Gateway container terminals, with the facilities expected to become operational within two years.

RIJEKA, Croatia – The Port of Rijeka is moving forward with its shore power development plans after awarding an €11.5 million contract to Croatian industrial group Končar for the design and installation of cold ironing infrastructure at its two container terminals. The contract is scheduled to be signed on Friday, November 27.
The announcement was made by Croatia’s Ministry of the Sea, Transport and Infrastructure. The agreement will be signed by Denis Vukorepa, Director of the Port of Rijeka Authority, and Gordan Kolak, President of Končar’s Management Board, in the presence of Deputy Prime Minister and Minister Oleg Butković.
The project aims to allow container ships to plug into the local electricity grid while docked and to turn off their own generators. This would help reduce emissions and noise pollution from port activities and thus create a cleaner operating environment.
The contract was awarded for approximately €11.5 million, excluding VAT, representing a reduction of more than €3.3 million compared with the initial tender estimate of €14.85 million. Three companies initially expressed interest in the procurement process: Serbia’s IEEC and Croatia-based ABB Zagreb and Končar. The latter two advanced to the subsequent technical solution development stage.
The planned infrastructure will provide a combined electrical capacity of 17.5 MW across the two terminals. The Adriatic Gate Container Terminal (AGCT), located in the Brajdica area, will receive 10 MW, while Rijeka Gateway, operated by APM Terminals, will be equipped with 7.5 MW.
Both facilities will also be fitted with dedicated electrical substations designed to adapt voltage and frequency to the technical requirements of vessels calling at the terminals. Construction activities will have to be carefully coordinated to ensure that commercial port operations can continue without interruption.
The investment is receiving substantial financial backing from the European Union through the Connecting Europe Facility (CEF). Under the wider POR2CORE-OPS project, eligible costs amount to €15.46 million, with 85% covered by EU funding, corresponding to a contribution of €13.14 million.
According to statements made by Vukorepa to Croatian newspaper Novi List, the shore power facilities are expected to be completed over the next two years. He believes Rijeka could become the first port in the Northern Adriatic to offer shore-side electricity connections for container vessels.
The initiative would also put the port ahead of the requirements introduced by European legislation from 2030, when shore-side electricity provision will become an increasingly important obligation for ports serving container and passenger ships.
The technical conditions required to carry out the project have already been secured through cooperation with Croatia’s national electricity company, HEP. This partnership is expected to support the implementation of the infrastructure and its integration into the existing electricity network.